Is plug-in solar legal in Maine?

Maine's LD 1730 (Public Law 2025, chapter 644) added 35-A MRSA §3475 and took effect July 29, 2026. Up to 420 W of combined inverter output per service address may be self-installed with no utility notice; systems over 420 W up to 1,200 W must be installed by a Maine-licensed electrician on a dedicated circuit with a single receptacle outlet and notified to the utility within 30 days. Plug-in systems are not eligible for net energy billing, so exported power earns nothing. The statute does not override leases or HOA rules.

StatusLaw in effect
LawLD 1730 (P.L. 2025, c. 644)
Effective dateJuly 29, 2026
System size cap1,200 W
OutletStandard outlet; systems over 420 W must use a dedicated circuit with a single receptacle outlet
Certification requirementMust be listed or certified in accordance with UL 3700 or a comparable standard by a nationally recognized testing laboratory, or configured in accordance with the National Electrical Code
InterconnectionNo interconnection application or agreement required; a system over 420 W must be notified to the utility within 30 days of installation
Utility rulesUtility may not require approval, an interconnection study, any fee, or additional controls or equipment, and may not deny a compliant installation

What this means for you

Use the legality checker to combine this state's rules with a specific product and your renter/homeowner status. Remember that a state law is only half of the answer — the product's UL 3700 certification status is the other half.

Sources (last checked 2026-11-23):

General information, not legal advice. Confirm against the statute text and your utility's current guidance.